Construction to begin at E.on's Rampion

UK: The first foundations will be installed at E.on's 400MW Rampion project off the UK's south coast this week (25 January).

E.on will install 116 MHI-Vestas V112 turbines at Rampion
E.on will install 116 MHI-Vestas V112 turbines at Rampion

Adverse weather had hampered seabed preparations, but installation is going ahead on schedule, E.on said.

Preparation work started in September and the first load of foundations was delivered in mid-January.

"I'm pleased that our highly skilled team have been able to overcome the poor weather conditions that we've faced over the last few weeks and continue with the construction of the wind farm as planned," said E.on's project development manager, Chris Tomlinson.

Rampion will comprise of 116 MHI-Vestas V112 3.45MW turbines at a site 13km off the UK's south coast, near Brighton.

E.on holds a 50.1% stake in the project following investments from the Green Investment Bank (25%) and Canadian energy firm Enbridge (24.9%).

Before commenting please read our rules for commenting on articles.

If you see a comment you find offensive, you can flag it as inappropriate. In the top right-hand corner of an individual comment, you will see 'flag as inappropriate'. Clicking this prompts us to review the comment. For further information see our rules for commenting on articles.

comments powered by Disqus

Windpower Offshore Events

Latest Offshore Wind Jobs