Dong completes Borkum Riffgrund 1 installations

GERMANY: All 78 Siemens 4MW turbines at Dong Energy's 312MW Borkum Riffgrund 1 have been installed.

The final Siemens 4MW turbine has been installed at Borkum Riffgrund 1
The final Siemens 4MW turbine has been installed at Borkum Riffgrund 1

Dong said approximately half of the turbines are connected to the grid, with the remaining units to be connected over the summer.

The first turbine was installed in October 2014, by vessel firm A2Sea. Installation suffered a minor delay after Siemens admitted manufacturing problems for its 4MW.

When the delay was announced in August 2014, Siemens said: "During the ramp up of serial production of this turbine, we experienced some limited delays in the manufacturing process.

"As a consequence, the start of the installation phase of the turbines at the project site will be delayed by a few weeks." Both Siemens and Dong said the commissioning date was unaffected.

The project is located 44 kilometres off the German coast in the North Sea.

Borkum Riffgrund 1 is majority owned by Dong (50%), with the remaining share being owned by Danish investment firms Kirkbi (32% and William Demant Invest

Have you registered with us yet?

Register now to enjoy more articles
and free email bulletins.

Sign up now
Already registered?
Sign in

Before commenting please read our rules for commenting on articles.

If you see a comment you find offensive, you can flag it as inappropriate. In the top right-hand corner of an individual comment, you will see 'flag as inappropriate'. Clicking this prompts us to review the comment. For further information see our rules for commenting on articles.

comments powered by Disqus

Windpower Offshore Events

Latest Offshore Wind Jobs