Westermost Rough fully online

UK: Dong Energy's 210MW Westermost Rough project has reached full output, less than two months after the final turbine was installed at the site.

Westermost Rough is the first commercial project to use the Siemens 6MW turbine
Westermost Rough is the first commercial project to use the Siemens 6MW turbine

Dong installed 35 Siemens 6MW turbines at the site, eight kilometres from England's north-east coast. It is the first commercial project to use the 6MW turbine.

First power from the project was produced at the start of September 2014, with the final turbine being installed in March. The developer said it is now working towards completing final testing.

According to Dong, 900 people were employed on the construction of the project, across the supply chain.

Earlier this month, regulator Ofgem named the Transmission Capital Partners (TCP) consortium as the preferred bidder for the project's transmission system.

Westermost Rough is majority owned by Dong (50%), with Marubeni Corporation and the UK Green Investment Bank each owning 25%.

Have you registered with us yet?

Register now to enjoy more articles
and free email bulletins.

Sign up now
Already registered?
Sign in

Before commenting please read our rules for commenting on articles.

If you see a comment you find offensive, you can flag it as inappropriate. In the top right-hand corner of an individual comment, you will see 'flag as inappropriate'. Clicking this prompts us to review the comment. For further information see our rules for commenting on articles.

comments powered by Disqus

Windpower Offshore Events

Latest Offshore Wind Jobs