Transformer installed at Meerwind

GERMANY: Seaway Heavy Lifting has installed the transformer at the 288MW Meerwind Sud/Ost project, the last of the major onsite construction milestones.

The Meerwind transformer being installed
The Meerwind transformer being installed

The 3,300 tonne topside of the transformer has now been installed on its foundation in water at a depth of 23 metres.

Seaway's crane vessel Oleg Stashnov completed the work at the project in the North Sea, 23 kilometres from the German coast.

Now that the transformer is in place, all work on the wind farm is complete, with the final turbine installed earlier this month. However, The HelWin1 grid connection to shore, which will serve the project, is not due to be completed until early autumn.

The project, which is being developed by WindMW, is made up of 80 Siemens 3.6MW turbines.

Before commenting please read our rules for commenting on articles.

If you see a comment you find offensive, you can flag it as inappropriate. In the top right-hand corner of an individual comment, you will see 'flag as inappropriate'. Clicking this prompts us to review the comment. For further information see our rules for commenting on articles.

comments powered by Disqus

Windpower Offshore Events

Latest Offshore Wind Jobs

Latest Offshore Wind Jobs