UK: Eon has finished the first phase of foundations installation at its 219MW Humber Gateway offshore project.

The location of the Humber Gateway project on Egland's east coast
The location of the Humber Gateway project on Egland's east coast
With 24 monopiles now driven into the seabed, the company is preparing for the next phase of construction, when the remaining 49 foundations will be put in place.

This work is expected to start in April.

Eon said that due to the scale of the upcoming work, it will be looking to employ a further 13 staff to join its operations team.

A £3 million (EUR 3.6 million) onshore facility has also been completed at the nearby Grimsby Fish Dock. This will accommodate the operations and maintenance team with offices, stores, a workshop and wind farm control room.

The EUR 880 million Humber Gateway project is located 8km off England's north east coast, and is expected to go online in 2015.

Have you registered with us yet?

Register now to enjoy more articles
and free email bulletins.

Sign up now
Already registered?
Sign in

Before commenting please read our rules for commenting on articles.

If you see a comment you find offensive, you can flag it as inappropriate. In the top right-hand corner of an individual comment, you will see 'flag as inappropriate'. Clicking this prompts us to review the comment. For further information see our rules for commenting on articles.

comments powered by Disqus

Windpower Offshore Events

Latest Offshore Wind Jobs