Germany

Germany

Global Tech foundations completed

GERMANY: WeserWind has completed the assembly of the last two tripod foundations for Windreich's Global Tech 1 project at its site in Bremerhaven.

Converter platform for Global Tech 1 project
Converter platform for Global Tech 1 project

The last foundations, ultimately destined for the 400MW wind farm in the German North Sea, have now been delivered by barge to the ABC-peninsula quay near Bremerhaven.

From here they will be shipped to the project site, 110 kilometres from shore.

All 80 foundations are expected to be in place by early 2014. The first Areva M5000-116 turbines were installed at the wind farm in September. Turbines will continue to be installed while the remaining tripod foundations are put in place.

The specially designed foundations weigh 900 tonnes and are 60 metres tall.

Before commenting please read our rules for commenting on articles.

If you see a comment you find offensive, you can flag it as inappropriate. In the top right-hand corner of an individual comment, you will see 'flag as inappropriate'. Clicking this prompts us to review the comment. For further information see our rules for commenting on articles.

comments powered by Disqus

Windpower Offshore Events

Latest Offshore Wind Jobs