Fisherman's setback for 25MW pilot plan

UNITED STATES: Fisherman's Energy has suffered a setback in its plan to build a 25MW offshore wind farm off the coast of New Jersey after it was rejected by the Public Utilities Commission (PUC).

The project was to be 4.5 kilometres east of Atlantic City in state waters and consist of six turbines. If approved, it would have been the first grid connected offshore project in the US.

The PUC has rejected the project on the grounds the state would be liable for up to $19.2 million if project funding through federal grants fell through. The total cost of the project would be $200 million.

Fisherman's Energy said it would "continue to work with the PUC" to develop the project.

In 2011, Fisherman's Energy, which is backed by commercial fishing firms, applied to the state Board of Public Utilities (BPU) for approval under new rules governing offshore wind.

The BPU had introduced the offshore wind renewable energy certificates programme, which will require projects to demonstrate a positive net economic impact on the state.

The second phase of the New Jersey project, planned to follow the demonstration phase, would be seven miles off the coast and have 66 turbines with a capacity of about 330MW.

Have you registered with us yet?

Register now to enjoy more articles
and free email bulletins.

Sign up now
Already registered?
Sign in

Before commenting please read our rules for commenting on articles.

If you see a comment you find offensive, you can flag it as inappropriate. In the top right-hand corner of an individual comment, you will see 'flag as inappropriate'. Clicking this prompts us to review the comment. For further information see our rules for commenting on articles.

comments powered by Disqus

Windpower Offshore Events

Latest Offshore Wind Jobs