United Kingdom

United Kingdom

First power at Gunfleet Sands 3

12MW demo project up and running

First power has been achieved at DONG Energy's Gunfleet Sands 3 development. It is now exporting power to the National Grid. The 12MW demo project – built 8.5km off Clacton-on-Sea in the Thames estuary – will host the first offshore tests of Siemens' new 6MW turbine.

Benj Sykes, DONG's UK country manager, said the project represented "a significant step in our work to reduce the cost of energy in offshore wind". The developer plans to install the Siemens 6MW units at its 240MW Westermost Rough project, planned for a site off the Yorkshire coast. It also recently agreed a deal with Siemens, for the supply of 154 of the 6MW turbines to the Gode Wind 1, 2 and 3 projects, in the German North Sea.

Have you registered with us yet?

Register now to enjoy more articles
and free email bulletins.

Sign up now
Already registered?
Sign in

Before commenting please read our rules for commenting on articles.

If you see a comment you find offensive, you can flag it as inappropriate. In the top right-hand corner of an individual comment, you will see 'flag as inappropriate'. Clicking this prompts us to review the comment. For further information see our rules for commenting on articles.

comments powered by Disqus

Windpower Offshore Events

Latest Offshore Wind Jobs